Notifiable project F10 form
The Construction (Design and Management) Regulations 2015 (CDM regulations) require that the Health and Safety Executive (HSE) must be notified of any project defined as construction under the regulations where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project, or exceed 500 person days. This can be done using an F10 form.
Regulation 6 of the CDM regulations requires that the client must give notice in writing to the HSE as soon as is practicable before the construction phase begins, or arrange for someone else to do this on their behalf.
The notice must include the details included in schedule 1 of the regulations:
- The date of forwarding the notice.
- The address of the construction site or precise description of its location.
- The name of the local authority where the construction site is located.
- A brief description of the project and the construction work that it entails.
- The following contact details of the client: name, address, telephone number and (if available) an email address.
- The following contact details of the principal designer: name, address, telephone number and (if available) an email address.
- The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.
- The date planned for the start of the construction phase.
- The time allocated by the client under regulation 4(1) for the construction work.
- The planned duration of the construction phase.
- The estimated maximum number of people at work on the construction site.
- The planned number of contractors on the construction site.
- The name and address of any contractor already appointed.
- The name and address of any designer already appointed.
- A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.
Where details are not available (such as the details of the principal contractor) they must be provided when they are available, and in any event, before construction works begin.
The notice must also be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work; and if necessary, be periodically updated.
HSE will take 10 days to process notifications by manual form. (Ref. HSE, F10 Manual input form frequently asked questions.) However, notification can now be carried out online by filling out an e-form and manual notification forms will cease to be available after 31 March 2015. Confirmation of receipt of an e-F10 form should be received shortly after submission.
[edit] Related articles on Designing Buildings
- Accident book.
- Accident report.
- CDM.
- CDM for self-builders and domestic clients.
- Competent person.
- Fee for intervention.
- First aider.
- Health and safety.
- Health and Safety Executive.
- Health and safety inspector.
- Incident reporting system.
- Inspections focus on occupational lung disease.
- Licence for Alterations for Apartment.
- Principal contractor.
- Reporting accidents and injuries on construction sites.
- Site records and registers.
- What approvals are needed before construction begins.
[edit] External references.
- HSE How to notify a project.
- Schedule 1 of the CDM regulations.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Comments